Implementation tracker

Guide Migration · Data in/Out · Center of excellence · three priority applications

9 Oct 2026
Programme phases (2)
Guide Migration
In Progress
6 of 8 tasks complete 75%
Started: 13 Aug 2026
Due: 30 Sep 2026

Guides migrated to 5 apps. Other guides were migrated successfully outside GX. Once Pendo installation is confirmed on the remaining apps, we will migrate those guides too.

✓
Migration scope alignment Done
✓
Migration work Done
✓
Tagging Enablement (for product teams) Done
✓
Guides Polish Enablement Done
✓
Push all guides out from GX Done
✓
Polish guides and target them Done
Test Guides in Stagging In progress 15 Sep – 30 Sep
Remove Gainsight tags NEXT 28 Sep – 30 Sep
Data in / Out
In Progress
1 of 4 tasks complete 25%
Started: 17 Aug 2026
Due: 6 Nov 2026

Snowflake integration is approved and in flight. We're moving to direct integration rather than a full pipeline build. Dell will follow up when Pendo is ready. Data is flowing from multiple apps, not only Elements and Payroll.

✓
Kickoff Call Done
Consultation meetings In progress 20 Aug – 29 Oct
Data Validation NEXT 8 Oct – 29 Oct
Knowledge Transfer 16 Oct – 6 Nov
Applications — active (3)
Staffology Payroll
→ Value slide
In Progress
6 of 9 tasks complete 67%
Started: 20 Aug 2026
Due: 13 Nov 2026

Analytics enablement went well in live Staffology; the team explored paths, funnels, and dashboards, and will retest segments after scoping eligibility to Staffology Payroll, with processing notes as the leading workflow use case.

✓
Install into Production Done
✓
Install Review Done
✓
Tagging Enablement Done
✓
Use Case Discovery Done
✓
Tagging Review Done
✓
Analytics Enablement Done
Establish Baselines NEXT 9 Oct – 23 Oct
Experience Activated 23 Oct – 6 Nov
Outcomes Measured 26 Oct – 13 Nov
IRIS Elements
In Progress
3 of 10 tasks complete 30%
Started: 11 Aug 2026
Due: 27 Nov 2026

Elements moved from GTM installation to direct snippet installation, with iframe support settings enabled as agreed. While we complete injection of the snippet into Tax so tagging works natively in those frames, the team can continue using the established GTM approach for Tax in the interim; we will confirm once the direct installation is live across both surfaces.

✓
Install completed Done
✓
Install Review/ Validation of Pendo Designer Done
✓
Tagging Enablement Done
Use Case Discovery NEXT 5 Oct – 16 Oct
Analytics Enablement 12 Oct – 23 Oct
Guides Enablement 19 Oct – 30 Oct
Establish Baselines 21 Oct – 6 Nov
Hands-on Workshops 21 Oct – 6 Nov
Experience Activated 5 Nov – 27 Nov
Outcomes Measured 11 Nov – 27 Nov
IAS
In Progress
2 of 5 tasks complete 40%
Started: 18 Aug 2026
Due: 13 Nov 2026

The 2 October track event review confirmed 106 events reaching Pendo with no data issues; production is live to a small cohort with wider rollout ahead, and product-area alignment with Elements is the main prep before analytics.

✓
Install Planning Done
✓
Confirm Track Events Done
Analytics Enablement NEXT 13 Oct
Establish Baselines 16 Oct – 30 Oct
Outcomes Measured 2 Nov – 13 Nov
Center of excellence